Welcome Media Center Customer Service Board of Directors Water Quality Publications Water Education
Home Los Vaqueros Employment Business Center Conservation
 

Expansion
Resources:

Expansion Home

LV Reservoir Expansion Studies

Los Vaqueros Watershed

 



 

 

 

 

 


LV Expansion Photo Gallery

These photos were taken prior to Oct. 11, 2011. To see photos taken after Oct. 11, look here.

Photos of the "Pressurized Grout Curtain"

Photos of the Spillway Construction

See our live LV Expansion Project Cam

We have videos on the Expansion Home Page


Workers edge toward milestone
The "toe" of of the dam is rising up as the last of the top of the dam is "shaved" in this photo taken on Oct. 11, 2011.
To the right, workers are compacting sand that assists drainage on the sides of the dam. To see a larger version of this photo, click here or on the photo.
Creating Face of Dam
A worker measures the angle on the face of the dam, as a bulldozer scrapes and compacts the dam to meet his measurements.
The ribbons on the sticks shows the bulldozer operator different angles in this photo taken on Oct. 11, 2011.
Overview of Wedge
Looking down on the top of the dam from the Crest Trail in this photo taken by CCWD Public Affairs Department Manager Jennifer Allen on Oct. 7, 2011, the "toe" of the dam is nearly to the top of the "shaved" existing dam. A "wedge" will be left at the top of the dam as workers continue to build up the reshaped "toe."
LV Expansion

The top of the spillway structure (mid-right) looms like a giant Mayan temple
or Egyptian pyramid in this photo by Aerial Photographer Dick Jones. While the top of the spillway's structure has been completed, there
is still much work to do on the stilling basin at the bottom of the spillway and finsihing work on the spillway itself. This photo was taken on Sunday,
Oct. 2, 2011 when there was no construction activity going on at the site. Click here or on the photo to see a larger version.

LV Expansion Spilway is Completed
Aerial Photographer Dick Jones took this sweeping shot of the project on Sunday, Oct. 2, 2011, when there was
no work at the site that day. The reshaped front of the dam and the existing dam are nearly at the same height. You can also
see the top of the dam's spillway (bottom center) and the "borrow" area to the mid-right where much of the 1 million
cubic yards of material needed for the expansion is being mined. Click here or on the photo to see a larger version.
Night work at Los Vaqueros Expansion
Two scrapers loaded with clay from the center of the dam move toward the clay storage area during night work
on Thursday, Sept. 29, 2011. Construction crews are now working 20 hours per day, six days a week.
Click here or on the photo to see a larger version.
Night Work at LV

Twp scrapers turn to pick up their loads of clay from the top of the dam
during night work on Sept. 29, 2011. At this point, the top of the dam has nearly been completely "shaved."
Click here or on this photo to see a larger version.

Workers remove the form from the spillway

Construction workers begin to dismantle the last form sections from the top of the spillway.
It took 43,000 cubic yards of roller compacted concrete to create the massive structure.
This photo was taken on Sept. 21, 2011.
Click here or on this photo to see a larger version.

Finished Spillway Structure
The major concrete-work on the top of the spillway was completed on Sept. 20. This photo was taken on Sept. 21, 2011.
Click here or on this photo to see a larger version
.
Lower Spillway

At the lower end of the spillway, workers continue to prepare
rebar for the first concrete pour for the stilling basin. This photo was taken on Sept. 21, 2011.
Click here or on the photo to see a larger version of this photo.


Inlet/Outlet Rebar
Construction workers move long pieces of rebar into position on the enlarged inlet/outlet structure on
Sept. 7, 2011. Click here or on this photo to see a larger version.
Spillway Form Work
Reusable forms for the ever-larger spillway structure are bolted into place on Sept. 7, 2011.
Spillway Form Work
One of the last sets of forms for the spillway structure are bolted into
place on Sept. 7, 2011.
Click here or on this photo to see a larger version.
Aerial Photographer Dick Jones took this photo looking straight down at the top of the dam on Sept. 1, 2011. At the bottom is the spillway structure. In the center is the dam itself with the new toe of the dam slightly to the left. Click on this photo or here to see a larger version of this photo.
You can see all of the work at the dam site in this photo shot Sept. 1, 2011 by Aerial Photographer Dick Jones. In the upper right
is the "borrow" area where much of the soil for the project is being mined.
Click on this photo, or here to see a larger version of this photo.
The rock that is being used for the right side of the dam is stored here, near the Kellogg Creek Picnic Area. Aerial Photographer
Dick Jones took this artful shot on Sept. 1, 2011. Click on the photo or here to view a larger version of this photo.
Overview of the Borrow Area

This is an overview of the borrow area where much of the material for the expanded dam is being mined.
The giant yellow scrapers transport the soil to the dam site. This site is located above and upstream of the dam.
This photo was taken on Aug. 30, 2011.
To see a larger version of this photo, click here or on the photo.

Overview of Dam

Here is another few of the dam construction activity, this time from the Crest Trail that starts near the Interpretive Center. Most dramatic, is the
the "toe" of the dam that is moving up in the middle of the picture, and the stone used on the right side of the dam. In the lower left hand side is
the deep stilling basin for the dam spillway. This photo was taken on Aug. 30, 2011
.
To see a larger version of this photo, click here or on the photo.

Overall Photo of Construction Aug. 25
The toe of the dam is moving up, while the top of the dam is moving down on this Aug. 25th photo. To the left, stone is used on this portion of the dam face In the foreground is the stilling basin for the spillway. To see a larger version of this photo, click here or on the photo.
Spillway Construction
Reusable forms are lifted off the face of the top of the new spillway. This is the downstream side of the dam. More than 35,000 cubic yards
of roller compacted concrete was used to built the spillway. This photo was taken on Aug. 25. To see a larger version of this photo, click here or on the photo.
Side Dumper

work on toe of the dam

Rock for the face of the dam is dumped on the toe of the dam on Aug. 25. 2011
Two massive bulldozers spread new material on the top of the toe of the dam on Aug. 25, 2011.
Spillway Rebar Work
Workers place rebar for the spillway near the bottom at the stilling basin. This photo was taken on Aug. 25, 2011.
Slices of the dam
Take a rare look of the different slices of material used to create a modern earthen dam. As the top of the dam is shaved, contractor
Barnard Construction is keeping the different types of material separate to use in the construction of the taller dam. In the foreground, the massive spillway continues to be poured. This photo was taken on Aug. 16, 2011.
To see a larger version of this photo, click here or on the photo.
Front of dam

The dam is going up and down at the same time. The toe of the dam (about the middle of the photo) is going up,
while for the first time the top of the dam is starting to noticeably drop for the first time. This photo was taken on Aug. 16, 2011.
To see a larger version of this picture, click here or on the photo.

Evening Photo of Work at LV Expansion

The moon shines over the Los Vaqueros Expansion Project during night work on Aug. 9, 2011. In the far left is the "Pressurized Grout Curtain"
on the shoulder of the dam. In the lower center is a storage yard near the spilling basin for the spillway. In the top right is
the construction on the top of the spillway, where the "continuing batch plant" (the large white tower)is creating the
35,000 cubic yards of "roller compacted concrete."
To view a larger version of this picture click here, or on the picture.

Top of dam at night
Looking down on the project, in the foreground, you can see the work on the spillway where the "roller compacted concrete"
is about to be poured. On the other side of the dam, the "pressurized grout curtain" work is underway. This photo was taken on Aug. 9, 2011.
To view a larger version of this picture click here, or on the picture.
Night Spillway Construction

A massive conveyor belt (left center) sends the "roller compacted concrete" to the top of the new spillway where workers and tractors begin
to spread the material out. More than 35,000 cubic yards of material will be used to form the top of the spillway. This photo was taken on
Aug. 9, 2011. To view a larger version of this picture click here, or on the picture.

Work on Inlet Structure

Workers prepare the rebar for the molds of the new inlet-outlet gates on the side of the reservoir
near the dam. This photo was taken on Aug. 4, 2011. To view a larger version of this picture click here, or on the picture.

Shoulder on Los Vaqueros Expansion
Construction crews clear the right side of the dam, which has been exposed prior to beginning to build up the side of the dam on Aug. 4, 2011.
To view a larger version of this picture click here, or on the picture.
Wotk on Toe of Dam
All kinds of tractors, compactors, scrapers and spreaders work on the "toe" of the dam
on Aug. 4, 2011 To view a larger version of this picture click here, or on the picture. Compare this photo to the one
taken on July 27 below and you can see how much material has been added.
Compare the height of the three concrete towers in the center of both photos.
A massive bulldozer digs into the top layer of the dam for the first time on Aug. 4, 2011. Located behind the bulldozer is the continuing batch plant.
Aerial Photo of Activity at LV on Aug. 1, 2011

There is a lot of activity at the Los Vaqueros Reservoir Expansion now. Aerial Photographer Dick Jones took this photo on Aug. 1, 2011
and we labeled some of the areas where progress on the expanding dam is taking place.

First New Dirt

The first new material has been added to the expanding Los Vaqueros Dam on July 27, 2011. The material was added to the toe of the dam.

 In the photo, you can see the new material being graded in the middle of the photo near the three "towers." 

The new earthen material will eventually rise to the top of the of the three towers, which are access tubes to equipment located below the dam.

Workers place steel curtains in an area near the top of the dam. This will be a storage area for the material used in the roller compacted concrete section of the spillway. This photo was taken on July 27, 2011
Continuous Batching Plant
The Continuing Batching Plant that will be used to mix roller compacted concrete for a section of the spillway
is being tested. It will start working in August and will operate 24-hours s day.
This photo was taken on July 21, 2011.Click here or on the photo to see a larger version.
Overall View

This view, shot on July 14, 2011, shows earth moving work being performed
on both sides of the dam. The earth and rocks are separated and stored in different locations at the watershed. Most of the rock will be crushed. The
abutments on both sides of the dam are being cleaned to the bedrock in preparation for the higher dam.
Click on the photo or here to see the detail in this photo.

Moving Earth at Los Vaqueros
An excavator fills a massive dump truck with soil in this photo taken above the north abutment on July 14, 2011. The soil being removed now will be used later to rebuild the dam.
A wheel-tractor scraper hauls massive rocks that will be crushed and then reused when the dam is rebuilt. This photo was taken on July 14, 2011.
Aerial Photo of Dam

Aerial Photographer Dick Jones is looking straight down at the the top of the dam in this photo taken June 30, 2011. Among the highlights of this photo, you can see the spillway being prepared and the many access roads cut into the face of the dam . Click on the photo or here to see the detail in this photo.

 

Pouring Concrete on the Spillway
Concrete is being poured for the new spillway in this photo take on July 7, 2011.
Spillway destruction

A jackhammer mounted on an excavator is being used in this photo to destroy a portion of the old concrete spillway at the top of the dam. This photo was taken on July 7, 2011.

 

Sweeping Aerial of Project Site
Aerial Photographer Dick Jones catches a sweeping photos of the project site, looking west toward Pleasanton.
This photo was shot on June 30,2011.
Work on Spillway
A worker climbs out of the spillway area, where rebar has been placed in preparation for the concrete pour. This photo was taken on June 30, 2011.
Looking at the dam underconstruction
More details of the spillway work on the face of the dam. This photo was taken on June 30, 2011.
Top of the Spillway
Up above the top of the dam, the old spillway is being removed. This photo was taken on June 30, 2011.
Aerial photo of dam site

This aerial was taken on June 2, 2011 by Dick Jones. You can see concrete forms being put
into place at the bottom of the spillway, and work collecting rocks on the borrow area
to the right above the dam.


Aerial of Dam Construction Showing Mt. Diablo
This aerial shot on June 11, 2011 gives an impressive perspective of the construction area all the way to Mt. Diablo.


Dam Expansion Underway

The huge mound of soil to the left will be used to form the "toe" of the expanded dam. In the middle, the work is just
starting on building the concrete forms for the enlarged spillway. This photo was taken on June 2, 2011.
You can click on this photo to view a much larger version .


Huge boulders are smashed into rock and soil with two giant rock crushers. This photo was taken on
June 2, 2011.



aerial of Dam Construction

This shot showing the dam was taken on May 2, 2011
by aerial photographer Dick Jones. Click
on this photo below to see a larger version.

This photo, also taken by aerial photographer Dick Jones
on May 2, 2011, dramatically shows the lowered reservoir
.

CCWD GM Jerry Brown
CCWD President Joseph L. Campbell

CCWD General Manager Jerry Brown speaks
at the Los Vaqueros Reservoir Partner
Appreciation Event on May 5, 2011.


CCWD President Joseph L. Campbell addresses
local, state and federal leaders at
the Los Vaqueros Reservoir Expansion
Partner Appreciation Event on May 5, 2011.

truck at LV

Drilling at Los Vaqueros Expansion

One of several articulated trucks being used
to haul dirt & material on May 3, 2011.


Drilling is underway on the
north abutment of the dam.

 
Bulldozer Above Dam

New roads carved into
the face of the dam and on the side on April 26, 2011.

A bulldozer clears land in one of the "borrow"
areas near the dam on April 25, 2011.
 
Looking down toward Walnut Blvd. and the Interpretive Center parking lot.
Much soil and rock will be stored in this area.
This photo was taken on April 25, 2011.
Face of LV Dam
Dumping rocks

On April 20, 2011, the face of the dam is starting to
change as a road is built across its face.

Rocks from the reservoir-side
of the dam have been moved
out of the way by massive articulated trucks on April 20,2011
 
Dam Expansion on 415
Tractor Works on hill
A bulldozer removes scrub and potions of the
Los Vaqueros Trail above the dam on April 15, 2011.
Some of the material for the taller dam will be excavated from this area.
A massive bulldozer navigates steep terrain
above the dam on April 15, 2011.
Steep Terrain
A portion of the retaining wall
above the dam is removed on April 15, 2011
More of the steep terrain in
the borrow area on April 15, 2011.
Road Below Dam
Work on Face of Dam

Work on the new temporary road below the dam is nearly
complete in this April 13, 2011 photo.

 

Construction crews are stripping the toe of the dam in
preparation of the expansion and stripping and
cleaning to the foundation on the abutments in anticipation
of the drilling and grouting of curtain wall on April 13, 2011.

lv EXPANSION ON 4-10-11

LV Expansion on 41011

The top of the dam on April 11, 2011 with the
reservoir at 50,000 acre-feet. No construction
has begun on the top at this point in
this early morning photo.

On April 11, 2011, an excavator begins to work
below the dam's spillway, removing rock
for a temporary road that will be built
below the dam. This was among the
first physical work done on the expansion.

LV Expansion on 41011
LV Dam Before Construction

At the top of the dam, an excavator
clears soil
on the hillside where the bathrooms
were located. This
photo was also shot on April 11, 2011.

The Los Vaqueros Dam before construction began
in this photo taken on March 3, 2011
 
PRINT | EMAIL THIS PAGE | SITE INDEX | SEARCH | CONTACT CCWD
HOME | MEDIA CENTER | WELCOME | WATER QUALITY | CUSTOMER SERVICE | BOARD OF DIRECTORS | WATER EDUCATION
PUBLICATIONS | EMPLOYMENT | BUSINESS CENTER | CONSERVATION | LOS VAQUEROS
Copyright © 2012 Contra Costa Water District