CONTRA COSTA WATER
DISTRICT
BOARD OF DIRECTORS
REGULAR MEETING
September
3, 2008
MINUTES
CALL TO ORDER
President
Campbell called to order a regular meeting of the Board of Directors of the
Contra Costa Water District at 6:30 p.m., at 1331 Concord Avenue, Concord,
the regular meeting place of the Board.
ROLL
CALL
Directors Present: Joseph
L. Campbell, President
Elizabeth
R. Anello, Vice President
Bette
Boatmun
John
A. Burgh
Karl L. Wandry
Acting General Manager: Jerry
D. Brown
Legal
Counsel: Robert
B. Maddow
District Secretary: Sharon L. Burris
President Campbell advised that
General Manager Bishop was out of town on District business and that Assistant General Manager Planning/Operations and Maintenance
Jerry Brown was Acting General Manager.
PLEDGE OF ALLEGIANCE
Director of Finance Brice Bledsoe led the pledge of allegiance.
ADOPTION OF AGENDA
Mr. Brown reported that there were no changes to the
agenda.
PUBLIC COMMENT
President Campbell asked if there were any public
comments. There were none.
CONSENT CALENDAR
1. Approve
Directors’ Services/Business and Travel Expenses
a. Future
Services – September
b. Expenses
– July/August
c. Compensation – August
2. Approve the following minutes:
a. July
16, 2008
b. August
6, 2008
3. Approve the warrant register dated September
4, 2008.
4. Adopt Resolution No. 08-24 authorizing
acceptance of a non-exclusive drainage pipeline easement from Save Mount
Diablo.
5. Adopt Resolution No. 08-25 adopting a
Mitigated Negative Declaration for the Downtown Concord Water Main Replacement
Project.
President Campbell and Director Boatmun pulled Agenda Item
No. 1.c. – Compensation – August.
MOTION: Boatmun/Burgh to approve the consent calendar
with the exception of Agenda Item No. l.c. – Compensation – August. The motion carried by a unanimous voice
vote.
1. Approve
Directors’ Services/Business and Travel Expenses
c. Compensation – August
Director Boatmun requested compensation for a California
Special District’s Association meeting on August 29, which occurred after the
adoption of the August calendar. President
Campbell also requested compensation for a site visit of the Alternative Intake
Project. The site visit was previously
scheduled for September; however due to a conflict it was rescheduled to August
27.
MOTION: Burgh/Anello to approve 1.c.
– Approve Directors’ Services/Business and Travel Expenses, Compensation –
August, as revised. The motion carried
by a unanimous voice vote.
ACTION
6. Award of Contract – Canal Loop Capacity Improvements
a. Authorize a budget transfer in the amount of
$330,000 from the Alternative Intake Project to the FY09 Untreated Water
Facilities Improvement Program budget; and
b. Authorize execution of a contract with
Con-Quest Contractors, Inc. for the construction of the Canal Loop Capacity
Improvements Project in the amount of $1,298,000, with an 8% change order
authority of $103,840, for a total amount not to exceed $1,401,840.
Mr. Brown reported that the item was placed on the action
calendar due to the dollar amount of the contract. The project would restore the canal loop
capacity. The project was presented to
the Operations and Engineering (O&E) Committee meeting on June 19. A budget transfer was needed to cover the
discrepancy between the engineer’s estimate and the low bid. He reported the discrepancy was because the
estimate didn’t account for the multiple sites where the work was going to
occur or for the special concrete work required.
President Campbell commented that the consulting engineer
did not evaluate this work even though he was advised to do so by the District.
Mr. Brown advised that staff was available
to give a presentation if the Board chose to have one.
President Campbell asked if there were any
public comments. There were none.
MOTION: Boatmun/Anello to
a) authorize a budget transfer in the amount of $330,000 from the Alternative
Intake Project to the FY09 Untreated Water Facilities Improvement Program
budget; and b) authorize execution of a contract with Con-Quest Contractors,
Inc. for the construction of the Canal Loop Capacity Improvements Project in
the amount of $1,298,000, with an 8% change order authority of $103,840, for a
total amount not to exceed $1,401,840.
The motion carried by a unanimous voice vote.
7. Award of Contract – Canal Levee
Elimination and Flood Mitigation Project, Phase 1 – Pipeline
a. Authorize execution of a contract with
Marques Pipeline, Inc., for construction of the Canal Levee Elimination and
Flood Mitigation Project, Phase 1 – Pipeline, in the amount of $7,375,000, with
a 13% change order authority of $958,750, for a total amount not to exceed
$8,333,750; and
b. Authorize an amendment to the Brown and
Caldwell Design Services Agreement for additional design services during
construction in the amount of $200,000, for a total amount not to exceed
$2,800,000.
Mr. Brown reported that the Board had previously awarded a
contract to clear the project site and prepare for the pipeline
installation. The project had been deferred
due to dry winter rain conditions and the uncertainty of potential impacts on
District operations resulting from Judge Oliver Wanger’s delta smelt
ruling. The project was last presented
to the O&E Committee on March 20. He
advised that Engineering Manager Rachel Lenci would be making a presentation.
Ms. Lenci reported that the project would improve public
safety and security, improve water quality and increase flood protection. Phase 1 of the project included the
installation of 1,900 feet of ten-foot diameter reinforced concrete pipe. It also included demolition of canal levees,
backfill of the canal from Pumping Plant 1 to Marsh Creek, and the installation
of stop logs for the Rock Slough Intake.
Future phases of the project were dependent upon additional funding
sources.
Using a map, Ms. Lenci identified the project location, the
Rock Slough Intake, Pumping Plant No. 1, and the area for Phase 1 of the
project. A review of the bid summary
indicated the lowest responsive bidder was Marques Pipeline, Inc., with a bid
of $7,375,000.
Ms. Lenci reviewed the fiscal impact of the project, which
included a 13% change order authority. The justification for the larger than normal
change order authority was attributed to potential variable soil conditions
beneath the existing canal and the potential of prolonged dry conditions during
the fall and winter which could necessitate an extension of the contract.
The design services agreement required an additional
$200,000 for biological monitoring and fish rescue activities. These activities were required as part of the
permitting and were not included in the initial project scope. District staff would continue to pursue the
appropriation in federal funds from the Water Resources Development Act (WRDA)
as well as through future WRDA funding.
Mr. Brown commented that even though there was increased certainty
with Judge Wanger’s decision there was still uncertainty associated with the
weather.
President Campbell commented that the project had been to
the O&E Committee on several occasions, and it was at the request of the
O&E Committee that the project was presented to the full Board.
President Campbell asked if there were any questions for
the presenter.
Director Burgh was very supportive of the project and commented
on the larger than normal change order authority. He noted that it was good engineering, good
management and good planning to be conservative on change orders up front since
unknown conditions often cannot be predicted accurately.
President Campbell asked if there were any public
comments. There were none.
MOTION: Wandry/Boatmun to
a) authorize execution of a contract with Marques Pipeline, Inc., for
construction of the Canal Levee Elimination and Flood Mitigation Project, Phase
1 – Pipeline, in the amount of $7,375,000, with a 13% change order authority of
$958,750, for a total amount not to exceed $8,333,750; and b) authorize an
amendment to the Brown and Caldwell Design Services Agreement for additional
design services during construction in the amount of $200,000, for a total
amount not to exceed $2,800,000. The
motion carried by a unanimous voice vote.
REPORTS FOR DISCUSSION
8. Committee Report(s)
a. Board
of Supervisors’ – Transportation, Water and Infrastructure Committee
Post-Meeting Report (8/18/08)
b. Retirement
Plan Committee Post-Meeting Report (8/22/08)
c. Finance
Committee Post-Meeting Report (8/25/08)
President
Campbell asked if there were any comments on the committee reports.
Director Burgh reported
that he would not be present at the September 17 Board meeting, when the Board
would be asked to formally adopt the recommendation of the Finance Committee
concerning disposition and reserve account adjustments. He had reviewed the Finance Committee’s report
and was pleased. He also agreed with the
planned allocations. He was in full
support of the Finance Committee’s recommendations and thanked staff for
producing savings that enable the District to be prudent in management for the
future.
9. Schedule Future Meeting Dates and Times
Director
Boatmun advised that she would be attending the Industrial Association meeting
on September 10.
REPORTS
10. General
Manager
Mr. Brown reported that the Board’s legislative visits to Washington, DC
scheduled for September 15-17 had been canceled. The legislators were unavailable due to both
the Republican Convention and the effects of Hurricane Gustav. The General Manager had discussed this with
President Campbell and Vice President Anello.
Mr. Bishop still planned to travel to Washington to meet with legislative
staff. If there was a need for an
impromptu meeting with a legislator, he would inform the Board President who
had agreed to fly back on short term notice.
Mr. Brown also reported that the legislature had passed SB
XX I and the bill was being sent to Governor Schwarzenegger for his signature.
11. Legal
Counsel
Mr. Maddow reported briefly on Fitzpatrick vs. CCWD. He advised that the case had been settled
within the parameters authorized by the Board.
He also reported briefly on the status of Judge Oliver Wanger’s hearings
concerning delta smelt. He advised that
the hearings were postponed until September 12.
He also reported on the salmon case and a biological opinion regarding
operation of the Central Valley Project pumps.
12. Board Members
Vice
President Anello did not have a report.
Director
Wandry reported that he would be out of town late next week and the week of
September 22.
Director
Burgh did not have a report.
President
Campbell did not have a report.
CLOSED SESSION
13.
Real Property Transaction as
allowed under Government Code Section 54656.8; Property: Water Supply
Contract: Negotiating Party: Golden State Water Company; District Negotiator: Walter J. Bishop, General Manager;
Issue: Instruct Negotiator on Terms and
Price.
At 6:55 p.m.,
President Campbell announced that the Board would move into closed
session. There was one matter before the
Board concerning real estate property negotiations. Acting General Manager Jerry Brown was the
General Manager’s designated
District negotiator. The additional
attendee would be the Assistant General Manger of Engineering/Construction
Steve Welch.
RECONVENE FROM CLOSED
SESSION
14. Report on closed session.
At 7:21 p.m.,
President Campbell reconvened the meeting and announced that the Board did not
take any action on the matter before it.
ADJOURNMENT
At 7:22 p.m., President Campbell adjourned the meeting to the next regular meeting of the Board of
Directors scheduled for September 17, 2008 commencing at 6:30 p.m.
Joseph
L. Campbell, President
ATTEST:
Sharon L. Burris
District Secretary